550 Terry A Francois Bl
San Francisco permit 202307051465 · Mission Bay
Scope of emergency generator permit is limited to only the emergency generators on the roof, & the associated supporting infrustructure for operation of these generators. this includes installing (x5) diesel generators on the roof, equipment anchorage, and fuel oil supply lines within a new shaft.
- Filed
- Jul 5, 2023
- Issued
- Feb 2, 2024 (7 months after filing)
- Completed
- Jan 16, 2025 (11 months after issuance)
- Review stops
- 19 stops across 3 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 5, 2023 | Jul 26, 2023 | — |
Redevelopment review Redevelopment · REDEV | Jul 26, 2023 | Aug 25, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jul 26, 2023 | Aug 29, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 26, 2023 | Aug 18, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 26, 2023 | Aug 13, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 26, 2023 | Jan 8, 2024 | — |
Electrical plan review Building Inspection · MECH-E | Aug 17, 2023 | Sep 11, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2023 | Oct 18, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2023 | Oct 16, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 27, 2023 | Oct 27, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 27, 2023 | Oct 27, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 28, 2023 | Nov 28, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 29, 2023 | Nov 29, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 18, 2023 | Dec 18, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 19, 2023 | Dec 19, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 19, 2023 | Dec 19, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Dec 22, 2023 | Approved |
Redevelopment review Redevelopment · REDEV | Dec 21, 2023 | Dec 28, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 8, 2024 | Feb 2, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $2,500,000
| Name | Role | License on permit |
|---|---|---|
| Russell E Sherman | Architect | C26698 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026