651 Geary St
San Francisco permit 202307051479 · Tenderloin
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Altered site permit for bpa #201706219947 -reduce scope, remove 2 of the 3 basement parking levels.delete all parking.revise ground floor layout & reduce size of remaining basement level.
- Filed
- Jul 5, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 23 stops across 5 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 5, 2023 | Jul 10, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Jul 10, 2023 | Sep 19, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 10, 2023 | In progress | — |
Building plan review Building Inspection · BLDG | Sep 19, 2023 | Oct 17, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 19, 2023 | Oct 4, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 19, 2023 | Oct 27, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2023 | Oct 6, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 10, 2023 | Oct 10, 2023 | Approved |
Building plan review Building Inspection · BLDG | Mar 18, 2024 | Mar 29, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 18, 2024 | Apr 3, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2024 | Mar 25, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 18, 2024 | Jan 23, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 18, 2024 | Mar 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 18, 2024 | Mar 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2024 | May 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 13, 2024 | May 30, 2024 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 24, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 13, 2024 | May 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2024 | May 31, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Frank Sung Fung Ed2 International | Architect | C8858 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026