San Francisco permit 202307061584 · Marina

ADUFull plan reviewFiled
Street view · Sep 2026
Google Street View of 2935 Fillmore St, Sep 2026
Scope of work
As written on the permit application.

Response to complaint# 2022-0693enf.existing 4th fl unit to be legalized under rh-3 dwelling density allowances.roof deck/52 sf)to be added to 4th fl unit.permit application split under 2022-012509prj

Timeline
Key dates from the city record.
Filed
Jul 6, 2023
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 5 departments
Comments issued
8 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 18, 2023Administrative

Zoning review

Planning · CP-ZOC

Oct 31, 2024Approved

Permit Processing Center

Building Inspection · PPC

In progress—

Building plan review

Building Inspection · BLDG

Nov 26, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 4, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 7, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 6, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 7, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 4, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Aug 11, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 18, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 18, 2025Approved

Fire prevention review

Fire Department · SFFD

Aug 21, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 11, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 6, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 11, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Aug 13, 2025Approved

Building plan review

Building Inspection · BLDG

In progress—

Fire prevention review

Fire Department · SFFD

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Development fee collection

Building Inspection · DFCU

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Filed
Estimated cost
$150,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Lawson Willard

Lawson Willard Architecture

ArchitectC26756
Jason Allen Pisano

Hom-Pisano Engineering Inc

EngineerC69708
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202307061584 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record