380 Christopher Dr
San Francisco permit 202307071659 · Inner Sunset
Kitchen remodl,exterior stucco repair and paint, vaulted ceiling nd foundation upgrade in front of building 2 (e) bathroom remodels on 2nd fl. new plumbing, replace windows and doors new 1st fl. bedroom and 1.5 baths, new mudroom new insulation and drywall, new water heater nd furnace expand livable
- Filed
- Jul 7, 2023
- Issued
- Aug 1, 2023 (within 1 month of filing)
- Completed
- Jul 30, 2024 (12 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 14 stops across 4 departments
- Comments issued
- None
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 7, 2023 | Jul 7, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 7, 2023 | Jul 7, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2023 | Jul 7, 2023 | — |
Intake Building Inspection · INTAKE | Jul 12, 2023 | Jul 12, 2023 | — |
Intake Building Inspection · INTAKE | Jul 13, 2023 | Jul 13, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 17, 2023 | Jul 17, 2023 | — |
Intake Building Inspection · INTAKE | Jul 19, 2023 | Jul 19, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 19, 2023 | Jul 19, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 19, 2023 | Jul 19, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 19, 2023 | Jul 19, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 19, 2023 | Jul 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 19, 2023 | Jul 20, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 19, 2023 | Jul 19, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2023 | Aug 1, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $380,000
| Name | Role | License on permit |
|---|---|---|
| Ethan C Andersen Drafting Cafe Architects | Architect | C34235 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2020