2 Northwood Dr
San Francisco permit 202307111878 · West of Twin Peaks
Single family residential renovation. finish (e) basement w/ (n) bedroom, 1.5 baths, laundryroom & family room, new foundation. 1 car covered parking to be maintained. no change to footprint or height.
- Filed
- Jul 11, 2023
- Issued
- Oct 27, 2023 (4 months after filing)
- Completed
- Feb 4, 2025 (15 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 18 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Public Works, Public Utilities
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 11, 2023 | Jul 11, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 11, 2023 | Jul 11, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Jul 11, 2023 | Jul 11, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | Jul 20, 2023 | Jul 20, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 20, 2023 | Jul 27, 2023 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Jul 27, 2023 | Jul 27, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 27, 2023 | Aug 22, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2023 | Sep 13, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 11, 2023 | Sep 12, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 13, 2023 | Sep 14, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Oct 3, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 3, 2023 | Oct 3, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 3, 2023 | Oct 5, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2023 | Oct 6, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 6, 2023 | Oct 11, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 11, 2023 | Oct 17, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 19, 2023 | Oct 19, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 19, 2023 | Oct 27, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $450,000
| Name | Role | License on permit |
|---|---|---|
| Rebecca Shaw Katkin Katkin Architecture | Architect | C-30747 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019