Scope of work
As written on the permit application.

Change of use on 3rd floor. t.i space to new massage establishment. electrical & mechanical are being dererred.

Timeline
Key dates from the city record.
Filed
Jul 11, 2023
Issued
Jun 5, 2024 (11 months after filing)
Completed
Dec 19, 2024 (6 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
30 stops across 6 departments
Comments issued
5 times, by Building Inspection
Put on hold
Once
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jul 14, 2023Administrative

Zoning review

Planning · CP-ZOC

Sep 14, 2023Administrative

Permit Processing Center

Building Inspection · PPC

May 8, 2024Administrative

Zoning review

Planning · CP-ZOC

Jan 30, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 12, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 7, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 29, 2024Administrative

Street use and mapping

Public Works · DPW-BSM

Feb 7, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 6, 2024Approved

Public health review

Public Health · HEALTH

Feb 6, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Mar 7, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Mar 26, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 21, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Mar 20, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 20, 2024Administrative

Zoning review

Planning · CP-ZOC

Mar 20, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 22, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 25, 2024Approved

Public health review

Public Health · HEALTH

Mar 21, 2024Approved

Street use and mapping

Public Works · DPW-BSM

May 1, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 22, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Apr 19, 2024Administrative

Zoning review

Planning · CP-ZOC

Apr 22, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 22, 2024Approved

Fire prevention review

Fire Department · SFFD

Apr 22, 2024Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Apr 22, 2024Approved

Public health review

Public Health · HEALTH

Apr 22, 2024Approved

Electrical plan review

Building Inspection · MECH-E

May 3, 2024Administrative

Electrical plan review

Building Inspection · MECH-E

May 3, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Jun 5, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$128,937
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Davis Yiucheung Ko

Davis Ko Architects

ArchitectC22090
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202307111912 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record