Scope of work
As written on the permit application.

Interior remodel of e single family dwelling, 2-story horizontal addition at rear of building. infill lightwell not visible from any site land. relocate rear exterior stairs, no change to front facade. no change to building height

Timeline
Key dates from the city record.
Filed
Jul 13, 2023
Issued
Sep 16, 2024 (14 months after filing)
Completed
Aug 12, 2026 (23 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 6 departments
Comments issued
8 times, by Building Inspection, Public Works
Put on hold
Once
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Jul 13, 2023—

Zoning review

Planning · CP-ZOC

Jul 13, 2023—

Zoning review

Planning · CP-ZOC

Jul 13, 2023Administrative

Zoning review

Planning · CP-ZOC

Aug 23, 2023Administrative

Zoning review

Planning · CP-ZOC

Sep 6, 2023Approved

Planning neighborhood notice

Planning · CP-NP

Sep 18, 2023Administrative

Permit Center

Permit Center · PERMIT-CTR

Nov 2, 2023—

Building plan review

Building Inspection · BLDG

Nov 8, 2023Administrative

Structural plan approval

Building Inspection · PAD-STR

Nov 8, 2023Administrative

Permit Center

Permit Center · PERMIT-CTR

Nov 15, 2023—

Central Permit Bureau

Building Inspection · CPB

Nov 17, 2023Administrative

Building plan review

Building Inspection · BLDG

May 21, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 12, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 25, 2024Issued Comments

Mechanical plan review quality control

Building Inspection · MECH-QC

Apr 25, 2024Administrative

Street use and mapping

Public Works · DPW-BSM

Apr 26, 2024Approved

Urban forestry

Public Works · DPW-BUF

May 29, 2024Issued Comments

Building plan review

Building Inspection · BLDG

May 29, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 29, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 5, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 18, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 18, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 26, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 26, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 15, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 18, 2024Approved

Urban forestry

Public Works · DPW-BUF

Aug 14, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 16, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 19, 2024Approved

Zoning review

Planning · CP-ZOC

Aug 29, 2024Approved

Permit Processing Center

Building Inspection · PPC

Sep 3, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Sep 16, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$690,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jeremiah W P Schaub

Schaub | Li | Architects

Authorized agent-othersC-32289
Man Yip Li

Schaub Li Architects

ArchitectC-39027
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202307132139 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record