678 23rd Av
San Francisco permit 202307132139 · Outer Richmond
Interior remodel of e single family dwelling, 2-story horizontal addition at rear of building. infill lightwell not visible from any site land. relocate rear exterior stairs, no change to front facade. no change to building height
- Filed
- Jul 13, 2023
- Issued
- Sep 16, 2024 (14 months after filing)
- Completed
- Aug 12, 2026 (23 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 32 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Public Works
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 13, 2023 | Jul 13, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 13, 2023 | Jul 13, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 13, 2023 | Jul 13, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Jul 17, 2023 | Aug 23, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 23, 2023 | Sep 6, 2023 | Approved |
Planning neighborhood notice Planning · CP-NP | Sep 8, 2023 | Sep 18, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Nov 2, 2023 | Nov 2, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 8, 2023 | Nov 8, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Nov 8, 2023 | Nov 8, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Nov 15, 2023 | Nov 15, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Nov 17, 2023 | Nov 17, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 17, 2023 | May 21, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 17, 2023 | Jan 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 26, 2024 | Apr 25, 2024 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Apr 25, 2024 | Apr 25, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 25, 2024 | Apr 26, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 26, 2024 | May 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 20, 2024 | May 29, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 20, 2024 | May 29, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 31, 2024 | Jun 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 12, 2024 | Jun 18, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 18, 2024 | Jun 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 25, 2024 | Jun 26, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 25, 2024 | Jun 26, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 26, 2024 | Jul 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 16, 2024 | Jul 18, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 18, 2024 | Aug 14, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2024 | Aug 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 19, 2024 | Aug 19, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 20, 2024 | Aug 29, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 3, 2024 | Sep 3, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 3, 2024 | Sep 16, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $690,000
| Name | Role | License on permit |
|---|---|---|
| Jeremiah W P Schaub Schaub | Li | Architects | Authorized agent-others | C-32289 |
| Man Yip Li Schaub Li Architects | Architect | C-39027 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022