2080 Mcallister St
San Francisco permit 202307142215 · Lone Mountain/USF
Comply w/nov20230792 for rear stairs to be removed. remove all lathe&plaster&sheetrock.all wall coverings on top 2 flrs.interior remodel to include kitchens,baths to all unit.convert portion of garage to habitable space connected to 1 unit.seismic upgrade per plans attached.sprinkler separate permit
- Filed
- Jul 14, 2023
- Issued
- Mar 1, 2024 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 14, 2023 | Jul 14, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 14, 2023 | Jul 14, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 14, 2023 | Jul 14, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 14, 2023 | Jul 14, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 14, 2023 | Jul 14, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jul 14, 2023 | Jul 14, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 18, 2023 | Aug 21, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 21, 2023 | Sep 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 23, 2023 | Nov 2, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 28, 2023 | Dec 5, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Dec 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 22, 2023 | Dec 27, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 27, 2023 | Dec 27, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 27, 2023 | Jan 31, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 31, 2024 | Feb 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 9, 2024 | Feb 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2024 | Feb 13, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 15, 2024 | Feb 15, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 15, 2024 | Mar 1, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $976,377
| Name | Role | License on permit |
|---|---|---|
| John Taylor Hood Hood Thomas Architects | Architect | C-14187 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026