217 Holly Park Cr
San Francisco permit 202307172328 · Bernal Heights
Interior renovation of 2-unit bldg. excavation at basement level for structural enhancements for (e) support (n) fixtures, finishes & windows. in-kind window + door replacement. excavation >50 y, does not exceed 8 vertical ft soil disturbance. no work outside exterior envelope. no work outside prow.
- Filed
- Jul 17, 2023
- Issued
- Dec 4, 2023 (5 months after filing)
- Completed
- Feb 5, 2026 (26 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 21 stops across 6 departments
- Comments issued
- Twice, by Building Inspection, Public Utilities
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 17, 2023 | Jul 17, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 17, 2023 | Jul 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 17, 2023 | Jul 17, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jul 17, 2023 | Jul 17, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2023 | Jul 17, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 26, 2023 | Jul 26, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Jul 26, 2023 | Jul 26, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 27, 2023 | Aug 1, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 1, 2023 | Sep 6, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 11, 2023 | Sep 29, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 29, 2023 | Sep 29, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 4, 2023 | Oct 11, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 11, 2023 | Oct 20, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 20, 2023 | Nov 2, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 2, 2023 | Nov 3, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 6, 2023 | Nov 7, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2023 | Nov 15, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 14, 2023 | Nov 15, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 15, 2023 | Nov 22, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 22, 2023 | Nov 22, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 22, 2023 | Dec 4, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $842,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Blau Spiegel Saw//Spiegel Ahara Workshop | Architect | C34488 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026