4 Ashbury Tr
San Francisco permit 202307182422 · Haight Ashbury
Int improvement. kitchen/bath remodel. new flooring/windows (not street visible) of existing. 2nd&3rd fl reconfiguration mep, struct, reinforcement @ basement lv. no excavation, no change to ext envelope, no facade work, no work in prow. (n) wdw on side, not street vis.
- Filed
- Jul 18, 2023
- Issued
- Jan 5, 2024 (6 months after filing)
- Completed
- Jan 14, 2025 (12 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 16 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 18, 2023 | Jul 18, 2023 | — |
Intake Building Inspection · INTAKE | Jul 31, 2023 | Jul 31, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jul 31, 2023 | Jul 31, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2023 | Aug 4, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 4, 2023 | Sep 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 21, 2023 | Oct 18, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 17, 2023 | Oct 23, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2023 | Oct 24, 2023 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Oct 24, 2023 | Dec 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 8, 2023 | Nov 8, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 21, 2023 | Dec 22, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 22, 2023 | Dec 26, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 26, 2023 | Dec 27, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 28, 2023 | Dec 29, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 29, 2023 | Dec 29, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 29, 2023 | Jan 5, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $390,000
| Name | Role | License on permit |
|---|---|---|
| Mark A Cruz Cruz Architecture & Design | Architect | C36564 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025