833 A Ingerson Av
San Francisco permit 202307202550 · Bayview Hunters Point
Convert partial of (e) garage into (n) adu with studio type(state government code section 65852.2 a through d.
- Filed
- Jul 20, 2023
- Issued
- Apr 13, 2026 (33 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 40 stops across 4 departments
- Comments issued
- 17 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 20, 2023 | Aug 10, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 10, 2023 | Aug 29, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 10, 2023 | Aug 30, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 10, 2023 | Sep 13, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2023 | Aug 15, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 10, 2023 | Jun 25, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2023 | Aug 15, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 10, 2023 | Aug 19, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 25, 2023 | Sep 22, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 6, 2024 | Feb 6, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 2, 2024 | May 14, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 2, 2024 | May 9, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 2, 2024 | May 15, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 2, 2024 | Jun 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 2, 2024 | May 14, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 2, 2024 | May 3, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 2, 2025 | Jan 16, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 2, 2025 | Jan 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 2, 2025 | Jan 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 2, 2025 | Jan 22, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 2, 2025 | Jan 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 2, 2025 | Feb 10, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 2, 2025 | Jan 3, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 30, 2025 | Jun 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 30, 2025 | Jul 1, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 30, 2025 | Jul 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2025 | Jul 2, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 30, 2025 | Jun 3, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 30, 2025 | Jun 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2025 | Jun 2, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 31, 2025 | Aug 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 31, 2025 | Aug 5, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 31, 2025 | Aug 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2025 | Aug 7, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2025 | Aug 5, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 31, 2025 | Aug 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2025 | Aug 8, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Aug 18, 2025 | Aug 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 19, 2025 | Aug 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2025 | Apr 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $121,997
| Name | Role | License on permit |
|---|---|---|
| Dan Lu Chen | Engineer | S5358 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026