377 Santa Ana Av
San Francisco permit 202307212752 · West of Twin Peaks
Renovation of detached, single-family residence to include: - raising the second floor level to accommodate a new roof deck; - new primary closet, work area and laundry addition at second floor; - new raised patio at first floor; - new partition walls for new bathroom and kitchen.
- Filed
- Jul 21, 2023
- Issued
- Apr 26, 2024 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 28 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Public Works
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 21, 2023 | Jul 25, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 25, 2023 | Mar 8, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 25, 2023 | Apr 12, 2024 | — |
Planning neighborhood notice Planning · CP-NP | Jan 22, 2024 | Jan 29, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 14, 2024 | Apr 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2024 | Mar 18, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2024 | Apr 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 12, 2024 | Apr 26, 2024 | Administrative |
Addendum 1: Final - arch,foundation, stell frame, mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 5, 2024 | Jun 13, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 11, 2024 | Jun 11, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 12, 2024 | Jun 12, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 13, 2024 | Jun 13, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2024 | Jun 13, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 13, 2024 | Aug 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 13, 2024 | Jul 29, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 13, 2024 | Jun 27, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 13, 2024 | Jun 26, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 13, 2024 | Oct 8, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2024 | Aug 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2024 | Sep 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 12, 2024 | Sep 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 17, 2024 | Sep 17, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2024 | Sep 26, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 27, 2024 | Sep 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 1, 2024 | Oct 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 1, 2024 | Oct 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 1, 2024 | Oct 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 8, 2024 | Oct 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $718,070
| Name | Role | License on permit |
|---|---|---|
| Michael James Hennessey Michael Hennessey Architecture | Architect | C31229 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025