2270 Folsom St
San Francisco permit 202307252946 · Mission
(e) at&t wireless facility modification: remove: 6 at&t ant. install: 3 new at&t ant in (e) footprint. install: 3 new nema dc6, 3 pwr trunks, 1 dc12, 1 batt string, 2 rectifiers, 1 6648 in (e) equip. area. new ant tops not to exceed bldg walls - no change to rad centers & overall height of bldg
- Filed
- Jul 25, 2023
- Issued
- Apr 11, 2024 (9 months after filing)
- Completed
- Oct 4, 2024 (6 months after issuance)
- Review stops
- 22 stops across 4 departments
- Comments issued
- 4 times, by Fire Department, Public Health, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 25, 2023 | Aug 11, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 11, 2023 | Aug 23, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 11, 2023 | Mar 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 23, 2023 | Sep 22, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 23, 2023 | Sep 28, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 23, 2023 | Sep 5, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Aug 23, 2023 | Aug 24, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 29, 2023 | Dec 15, 2023 | Approved |
Public health review Public Health · HEALTH | Nov 29, 2023 | Mar 6, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 29, 2023 | Nov 30, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Nov 30, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 29, 2023 | Nov 29, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 29, 2023 | Dec 1, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 3, 2024 | Jan 4, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 3, 2024 | Feb 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 3, 2024 | Jan 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 3, 2024 | Jan 19, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 2, 2024 | Feb 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 2, 2024 | Feb 7, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 2, 2024 | Feb 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 2, 2024 | Feb 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 25, 2024 | Apr 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $60,000
| Name | Role | License on permit |
|---|---|---|
| Joseph Russell King | Engineer | C93286 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026