250 Locust St
San Francisco permit 202307283188 · Presidio Heights
Renovation, window additions @ set-back stucco portion of (e) bldg, no changes to brick elevations/building height. structural stregthening @ ground/f, roof deck w/in (e)stem walls. no visible adjustments from public way.
- Filed
- Jul 28, 2023
- Issued
- Nov 28, 2023 (4 months after filing)
- Completed
- Jan 30, 2026 (26 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 15 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 28, 2023 | Jul 28, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Jul 28, 2023 | Jul 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2023 | Jul 28, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 28, 2023 | Jul 28, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2023 | Aug 2, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 2, 2023 | Sep 6, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 9, 2023 | Oct 18, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Nov 1, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2023 | Nov 3, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2023 | Nov 6, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2023 | Nov 13, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 14, 2023 | Nov 16, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 20, 2023 | Nov 21, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 21, 2023 | Nov 21, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 21, 2023 | Nov 28, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,500,000
| Name | Role | License on permit |
|---|---|---|
| Malcolm Christopher Davis Malcolm Davis Architecture | Architect | C23744 |
| Jason R Powers Zfa Structural Engineers | Engineer | 76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2009