962 Key Av
San Francisco permit 202307283260 · Bayview Hunters Point
Rear 3-story addition to (e) 2-story home including removal of previous addition, kitchen remodel, (n) deck & main & upper levels & access stair to rear yard.
- Filed
- Jul 28, 2023
- Issued
- Oct 17, 2025 (27 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 44 stops across 6 departments
- Comments issued
- 11 times, by Building Inspection, Fire Department, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 28, 2023 | Aug 9, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 9, 2023 | May 29, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 9, 2023 | Sep 19, 2025 | Administrative |
Building plan review Building Inspection · BLDG | May 30, 2024 | Jun 28, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 30, 2024 | Jul 15, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 30, 2024 | Jul 1, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2024 | Jun 3, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 1, 2024 | Jul 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 25, 2024 | Oct 10, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2024 | Oct 30, 2024 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Nov 25, 2024 | Nov 25, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 3, 2024 | Dec 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 9, 2024 | Dec 12, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 9, 2024 | Jan 22, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 9, 2024 | Jan 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 9, 2024 | Dec 17, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 9, 2024 | Dec 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 19, 2024 | Dec 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 19, 2024 | Mar 7, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 19, 2024 | Dec 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 19, 2024 | Jan 2, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 29, 2025 | Jan 29, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2025 | Oct 17, 2025 | Administrative |
Development fee collection Building Inspection · DFCU | Sep 19, 2025 | Sep 19, 2025 | Administrative |
Addendum 1: Final-architectural, foundation, t24,mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 28, 2025 | Nov 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 14, 2025 | Nov 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Nov 14, 2025 | Feb 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Nov 14, 2025 | Dec 18, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 14, 2025 | Dec 19, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2025 | Dec 2, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 14, 2025 | Nov 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2025 | Nov 19, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Nov 14, 2025 | Dec 15, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2025 | Nov 20, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 14, 2025 | Mar 3, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2025 | Dec 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2026 | Feb 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 28, 2026 | Feb 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 28, 2026 | Feb 4, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 28, 2026 | Feb 2, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 28, 2026 | Mar 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2026 | Jan 29, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Feb 18, 2026 | Feb 18, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2026 | Mar 20, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $475,129
| Name | Role | License on permit |
|---|---|---|
| Brandon D Marshall Fog Studio | Architect | C-33665 |
| Lou Xiao Lx Engineering | Engineer | S5130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022