377 Park St #0
San Francisco permit 202307313330 · Bernal Heights
215 sq ft side addition @ the 3rd fl of a 3 story two family residential bldg. new side addition converting side poriton of (e)3rd fl into front & rear deck;new skylights & solatubes
- Filed
- Jul 31, 2023
- Issued
- May 16, 2024 (10 months after filing)
- Completed
- Dec 29, 2025 (19 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 35 stops across 5 departments
- Comments issued
- 7 times, by Planning, Building Inspection, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 31, 2023 | Aug 11, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 11, 2023 | Feb 21, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 11, 2023 | May 15, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 28, 2024 | Feb 28, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 28, 2024 | Mar 15, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 28, 2024 | Mar 15, 2024 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Feb 28, 2024 | Mar 7, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 28, 2024 | Mar 12, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 15, 2024 | Mar 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2024 | May 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 9, 2024 | May 14, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 9, 2024 | May 9, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2024 | May 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 15, 2024 | May 16, 2024 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 12, 2024 | Jun 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 13, 2024 | Jun 13, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jun 18, 2024 | Jun 18, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 20, 2024 | Jun 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2024 | Jun 25, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 25, 2024 | Jul 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2024 | Jul 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2024 | Jun 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2024 | Jul 9, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 25, 2024 | Sep 12, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jun 26, 2024 | Jul 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 15, 2024 | Aug 27, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2024 | Aug 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2024 | Sep 6, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 15, 2024 | Aug 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2024 | Aug 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 29, 2024 | Sep 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 29, 2024 | Sep 3, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 29, 2024 | Sep 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 12, 2024 | Apr 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $128,457
| Name | Role | License on permit |
|---|---|---|
| Michael Iain Hannah Mihmic Architecture Inc. | Architect | C35073 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025