900 Bush St
San Francisco permit 202308023549 · Nob Hill
Exterior common area renovation for waterproofing, associated hardscape, and associated landscape at existing plaza decks only. (not visible from street) (e) footprint of (e) building to remain no change.
- Filed
- Aug 2, 2023
- Issued
- Nov 6, 2025 (27 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 30 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Aug 2, 2023 | Aug 2, 2023 | Administrative |
Intake Building Inspection · INTAKE | Aug 2, 2023 | Aug 2, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 2, 2023 | Aug 2, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 2, 2023 | Aug 2, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 3, 2023 | Aug 3, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 3, 2023 | Aug 3, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 3, 2023 | Aug 3, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 17, 2023 | Aug 17, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 20, 2023 | Sep 20, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 20, 2023 | Sep 20, 2023 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 20, 2023 | Sep 20, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 20, 2023 | Sep 20, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Sep 21, 2023 | Sep 28, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Sep 28, 2023 | Oct 30, 2023 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Feb 21, 2025 | Feb 21, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 21, 2025 | Mar 14, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 21, 2025 | Jul 11, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Apr 11, 2025 | Apr 21, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 11, 2025 | Apr 15, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 11, 2025 | Apr 21, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 11, 2025 | Apr 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 17, 2025 | Apr 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 18, 2025 | Jun 18, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jun 18, 2025 | Jul 2, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 18, 2025 | Jun 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 18, 2025 | Jun 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2025 | Jul 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 11, 2025 | Oct 20, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2025 | Nov 6, 2025 | Administrative |
Building Inspection 417-86 | Oct 21, 2025 | Nov 6, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $3,000,000
| Name | Role | License on permit |
|---|---|---|
| Adrian N Blanco | Architect | C-32270 |
| Marc Dimalanta D-Scheme Studio | Architect | C-33350 |
| Akuavi Hine Murphy Burr Curry Inc | Engineer | S6470 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026