1117 Market St
San Francisco permit 202308033645 · South of Market
G/f & 2/f: new office partitions, ceiling, lighting, power/data, casework, signage, toilet accessories, interior stair, interior windows
- Filed
- Aug 3, 2023
- Issued
- Jul 9, 2025 (23 months after filing)
- Completed
- May 28, 2026 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 21 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 3, 2023 | Aug 3, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 3, 2023 | Aug 3, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 3, 2023 | Aug 3, 2023 | Administrative |
Code enforcement Building Inspection · CES | Aug 3, 2023 | Aug 3, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 4, 2023 | Aug 4, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 9, 2023 | Aug 14, 2023 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Aug 10, 2023 | Aug 10, 2023 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Aug 11, 2023 | Aug 11, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 14, 2023 | Aug 24, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 23, 2023 | Aug 30, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 24, 2023 | Aug 24, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 29, 2023 | Aug 29, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 30, 2023 | Sep 12, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 12, 2023 | Sep 18, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 18, 2023 | Oct 5, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 12, 2023 | Oct 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 12, 2023 | Oct 16, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2023 | Oct 17, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 17, 2023 | Oct 17, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 19, 2023 | Oct 19, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 19, 2023 | Jul 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,371,959
| Name | Role | License on permit |
|---|---|---|
| Anne Marie Cervantes Cervantes Design Assoc. | Architect | C-18037 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025