1750 Mission St
San Francisco permit 202308033650 · Mission
Abate nov#202304869. legalize existing non-permitted dweling unit (unit 1752a & 1752b) at 1/f (unit 1752a: 1,456 floor area, unit 1752b: 428 sf). modify rear shed. change of use from b/r-2 to r-2 (g/f only).
- Filed
- Aug 3, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 73 stops across 5 departments
- Comments issued
- 38 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 3, 2023 | In progress | In Progress |
Zoning review Planning · CP-ZOC | Sep 15, 2023 | Jan 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 15, 2023 | Sep 27, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 15, 2023 | Oct 23, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 15, 2023 | Oct 17, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 15, 2023 | Jan 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2023 | Sep 19, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Sep 15, 2023 | Sep 26, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Sep 26, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 15, 2023 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 17, 2024 | Apr 24, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 18, 2024 | May 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 18, 2024 | May 15, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 18, 2024 | May 10, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 18, 2024 | Apr 30, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 19, 2024 | Apr 23, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 22, 2024 | Apr 22, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 22, 2024 | Apr 22, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 13, 2024 | May 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 5, 2024 | Sep 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 5, 2024 | Aug 19, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2024 | Aug 5, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2024 | Aug 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 5, 2024 | Aug 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2024 | Aug 7, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 5, 2024 | Sep 10, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2024 | Aug 6, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 5, 2024 | In progress | — |
Building plan review Building Inspection · BLDG | Dec 5, 2024 | Jan 13, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 5, 2024 | Jan 6, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2024 | Dec 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 5, 2024 | Dec 6, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2024 | Dec 11, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 5, 2024 | Feb 5, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2024 | Dec 19, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 13, 2025 | Jan 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 13, 2025 | Jan 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 13, 2025 | Jan 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 13, 2025 | Jan 13, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2025 | Jan 14, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 12, 2025 | Mar 25, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 12, 2025 | Mar 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2025 | Mar 24, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 12, 2025 | Mar 24, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 12, 2025 | Mar 13, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 12, 2025 | Apr 22, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 12, 2025 | Mar 17, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 9, 2025 | Sep 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 11, 2025 | Sep 30, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 11, 2025 | Sep 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 11, 2025 | Sep 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 11, 2025 | Oct 14, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2025 | Sep 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 11, 2025 | Sep 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 10, 2025 | Nov 26, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 10, 2025 | Nov 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 10, 2025 | Nov 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 10, 2025 | Dec 1, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 10, 2025 | Nov 18, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 10, 2025 | Nov 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 10, 2025 | Nov 13, 2025 | Approved |
Apartment and hotel inspection Building Inspection · HIS | Oct 8, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Oct 8, 2026 | Oct 29, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 8, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 8, 2026 | Oct 13, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 8, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Oct 8, 2026 | Oct 8, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 8, 2026 | Oct 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 8, 2026 | Oct 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $328,000
| Name | Role | License on permit |
|---|---|---|
| Erik Stanton Chan | Architect | C-24663 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024