51 Lopez Av
San Francisco permit 202308033667 · West of Twin Peaks
1/f: alteration at gym.garage area 48 sq ft additional heated floor area. (n) bathroom. relocae washer/dryer under stair. small cooktop and refer at kitchenette.2nd fl: infill wall openings & replace door with window. remove juliette balcony. infill portion of wall at lounge for shear wall.
- Filed
- Aug 3, 2023
- Issued
- May 15, 2024 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 22 stops across 3 departments
- Comments issued
- 4 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 3, 2023 | Aug 3, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 4, 2023 | Aug 4, 2023 | Issued Comments |
Intake Building Inspection · INTAKE | Aug 7, 2023 | Aug 7, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 7, 2023 | Aug 7, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 7, 2023 | Aug 7, 2023 | Issued Comments |
Intake Building Inspection · INTAKE | Sep 20, 2023 | Sep 20, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 20, 2023 | Sep 20, 2023 | Approved |
Intake Building Inspection · INTAKE | Dec 20, 2023 | Dec 20, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 20, 2023 | Dec 20, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2023 | Dec 20, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 20, 2023 | Dec 20, 2023 | Administrative |
Intake Building Inspection · INTAKE | Mar 5, 2024 | Mar 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 6, 2024 | Mar 6, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Apr 22, 2024 | Apr 22, 2024 | Approved |
Intake Building Inspection · INTAKE | Apr 29, 2024 | Apr 29, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2024 | Apr 29, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 29, 2024 | Apr 29, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2024 | Apr 29, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 30, 2024 | Apr 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 6, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2024 | May 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 15, 2024 | May 15, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $185,985
| Name | Role | License on permit |
|---|---|---|
| Steven Carl Geiszler Steven Geiszler | Architect | C-24557 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026