2534 Great Hy
San Francisco permit 202308033695 · Sunset/Parkside
3rd story vertical addition; (e) small 3rd story room will be removed) and inteiror alt including new windows and cladding at front and rear facades. new exterior stair at rear.
- Filed
- Aug 3, 2023
- Issued
- Mar 7, 2025 (19 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 6 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 3, 2023 | Aug 11, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 11, 2023 | Apr 30, 2024 | Approved |
Planning neighborhood notice Planning · CP-NP | Nov 8, 2023 | Nov 15, 2023 | Approved |
Building plan review Building Inspection · BLDG | May 1, 2024 | Jun 25, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2024 | Jul 17, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2024 | Jul 18, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 18, 2024 | Sep 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 17, 2024 | Sep 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 16, 2024 | Oct 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 16, 2024 | Oct 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 12, 2024 | Nov 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 18, 2024 | Dec 18, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 18, 2024 | Dec 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 18, 2024 | Jan 3, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 5, 2025 | Feb 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2025 | Feb 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 24, 2025 | Mar 3, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 4, 2025 | Mar 5, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 5, 2025 | Mar 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $625,000
| Name | Role | License on permit |
|---|---|---|
| Joshua Lowe Juniper Architecture | Architect | C34764 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022