3470 Mission St #0
San Francisco permit 202308043835 · Bernal Heights
To comply with nov 202309077. storefront window replacement due to car crashing to the suite. underslab concrete repair @ basement w/in sidewalk due to car crashing in suite
- Filed
- Aug 4, 2023
- Issued
- Jul 16, 2024 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 21 stops across 4 departments
- Comments issued
- 4 times, by Planning, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Aug 4, 2023 | Aug 4, 2023 | — |
Intake Building Inspection · INTAKE | Aug 4, 2023 | Aug 4, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 11, 2023 | Aug 11, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 11, 2023 | Aug 11, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 11, 2023 | Aug 11, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2023 | Aug 11, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 11, 2023 | Aug 11, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2023 | Aug 11, 2023 | Issued Comments |
Intake Building Inspection · INTAKE | Aug 30, 2023 | Aug 30, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 30, 2023 | Aug 30, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 6, 2023 | Sep 6, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 6, 2023 | Sep 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 6, 2023 | Sep 6, 2023 | Issued Comments |
Intake Building Inspection · INTAKE | Sep 22, 2023 | Sep 22, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 22, 2023 | Sep 22, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 27, 2023 | Sep 27, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 27, 2023 | Sep 27, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 27, 2023 | Sep 27, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 27, 2023 | Sep 27, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 16, 2024 | Jul 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 16, 2024 | Jul 16, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $37,000
| Name | Role | License on permit |
|---|---|---|
| Marco Cham-Yin Fung Archites Studio | Architect | C32363 |
| Robert Hugh Shaffer Morris Shaffer Engineering | Engineer | C45322 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025