450 Pacific Av #0
San Francisco permit 202308154476 · North Beach
Deferred structural scope from 202307172307 including removal of approximately 50% of level 3. new diaphragm strengthening to levels 2, 3 & 4. addition of stability bracing to seismic braces at gl3.7. infill.
- Filed
- Aug 15, 2023
- Issued
- Nov 2, 2023 (3 months after filing)
- Completed
- Sep 4, 2024 (10 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 13 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 15, 2023 | Aug 15, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 15, 2023 | Aug 15, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2023 | Aug 15, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 15, 2023 | Aug 15, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 16, 2023 | Aug 16, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 16, 2023 | Sep 18, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 16, 2023 | Aug 16, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 5, 2023 | Oct 16, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 18, 2023 | Oct 20, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2023 | Oct 24, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 25, 2023 | Oct 26, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 30, 2023 | Oct 30, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 30, 2023 | Nov 2, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,131,565
| Name | Role | License on permit |
|---|---|---|
| Mark P Sarkisian Skidmore, Owings & Merrill | Architect | S-4639 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026