2266 Vallejo St
San Francisco permit 202308154490 · Marina
Horizontal addition(50 square ft)@ rear of level 5,northeast corner.addition is set back 3ft from east property line.raise rear roof of bldg 6"@ back of residence over office.replace (e)stone tile paving @(e)level 5 rear balcony.replace(e)sliding door @ level 5 rear balcony with (n)unit.
- Filed
- Aug 15, 2023
- Issued
- Apr 23, 2024 (8 months after filing)
- Completed
- May 5, 2025 (12 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 15, 2023 | Aug 22, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 22, 2023 | Dec 21, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 22, 2023 | Apr 12, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Nov 1, 2023 | Nov 8, 2023 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Dec 22, 2023 | Feb 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 22, 2023 | Feb 22, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 22, 2023 | Jan 29, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 22, 2023 | Mar 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 22, 2023 | Jan 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2023 | Jan 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 23, 2024 | Jan 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 31, 2024 | Feb 1, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 31, 2024 | Apr 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 31, 2024 | Feb 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 31, 2024 | Feb 2, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 14, 2024 | Apr 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 14, 2024 | Mar 19, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 14, 2024 | Mar 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 14, 2024 | Apr 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2024 | Mar 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2024 | Mar 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 12, 2024 | Apr 23, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $95,000
| Name | Role | License on permit |
|---|---|---|
| Marissa Tweedie Brandon Marissa Brandon Architect | Authorized agent-others | C25916 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022