888 Brannan St
San Francisco permit 202308164591 · South of Market
4th fl - ti including construction of new non-structural partitions, new accoustical grid & tile ceilings & gyp board ceilings; new electrical & lighting, new finishes throughout, new mech, electrical & plumbing equipment
- Filed
- Aug 16, 2023
- Issued
- Sep 13, 2023 (within 1 month of filing)
- Completed
- Apr 26, 2024 (7 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 14 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 16, 2023 | Aug 16, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 16, 2023 | Aug 16, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 22, 2023 | Aug 22, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 23, 2023 | Aug 23, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 23, 2023 | Aug 23, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 24, 2023 | Aug 24, 2023 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Aug 25, 2023 | Aug 25, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 25, 2023 | Aug 25, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 29, 2023 | Aug 29, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 12, 2023 | Sep 12, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 12, 2023 | Sep 12, 2023 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Sep 12, 2023 | Sep 12, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 13, 2023 | Sep 13, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2023 | Sep 13, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1,500,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Craig Pamperin | Architect | C-31455 |
| Barry Steven Wenger | Engineer | S7036 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2016