388 Market St
San Francisco permit 202308174602 · Financial District/South Beach
8/f-suite 888: t.i., 964 sq. ft. new glass partition system for conference room, electrical/mechanical upgrade, break room
- Filed
- Aug 17, 2023
- Issued
- Sep 6, 2023 (within 1 month of filing)
- Completed
- Dec 28, 2023 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 7 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 17, 2023 | Aug 17, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 17, 2023 | Aug 17, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 17, 2023 | Aug 17, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 29, 2023 | Aug 29, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 29, 2023 | Aug 29, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 29, 2023 | Aug 29, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 6, 2023 | Sep 6, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $256,000
| Name | Role | License on permit |
|---|---|---|
| Mohammad Sharif Rahimian Atelier 424 | Architect | C25912 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026