1905 Union St
San Francisco permit 202308224942 · Marina
To comply with nov 202286294 & 202286803. existing roof deck expansion. comply with 2022-000732enf (newly construction deck exceeds that allowed under pa 202201206346 & 201404163371).
- Filed
- Aug 22, 2023
- Issued
- Oct 30, 2024 (14 months after filing)
- Completed
- May 12, 2025 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 7 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Aug 22, 2023 | Aug 22, 2023 | Approved |
Intake Building Inspection · INTAKE | Aug 22, 2023 | Aug 22, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 22, 2023 | Sep 12, 2023 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 13, 2023 | Sep 13, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Sep 19, 2023 | Sep 19, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | Sep 20, 2023 | Sep 20, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 20, 2023 | Sep 28, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 28, 2023 | Feb 22, 2024 | Approved |
Planning neighborhood notice Planning · CP-NP | Jan 29, 2024 | Jan 29, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 27, 2024 | Feb 28, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 29, 2024 | Mar 19, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 20, 2024 | May 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 2, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 29, 2024 | Jul 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 4, 2024 | Jun 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2024 | Jul 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 30, 2024 | Jul 30, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 14, 2024 | Aug 14, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 16, 2024 | Aug 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 6, 2024 | Sep 6, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 1, 2024 | Oct 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 1, 2024 | Oct 3, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 4, 2024 | Oct 23, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 24, 2024 | Oct 28, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 28, 2024 | Oct 30, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $12,000
| Name | Role | License on permit |
|---|---|---|
| William Geoffrey Walters Disseny | Architect | C20271 |
| Victor Ramos Ashley & Vance Engineering | Engineer | C86568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026