261 Broad St
San Francisco permit 202308245158 · Oceanview/Merced/Ingleside
Erect 2-story over 1 basement, type v-b, residential care facility. merge lots parcels 7114/038 and 7114/039. (263 broad st, parcel 7114/038 is currently a vacant lot). (ref demo of 261 broad st, parcel 7114/039 under pa# 202308245160).
- Filed
- Aug 24, 2023
- Issued
- Aug 4, 2025 (23 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 59 stops across 6 departments
- Comments issued
- 25 times, by Building Inspection, Fire Department, Public Works, Permit Center, Planning
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 24, 2023 | Sep 5, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 5, 2023 | Jul 30, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 5, 2023 | Jul 8, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Aug 1, 2024 | Sep 3, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 1, 2024 | Aug 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 1, 2024 | Sep 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 1, 2024 | Aug 2, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 2, 2024 | Dec 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 11, 2024 | Oct 11, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 15, 2024 | Oct 18, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 16, 2024 | Oct 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 7, 2024 | Nov 7, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 18, 2024 | Nov 20, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 5, 2024 | Dec 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 26, 2024 | Jan 23, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 5, 2025 | Mar 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 19, 2025 | Mar 26, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 19, 2025 | May 7, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 19, 2025 | Mar 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2025 | Mar 24, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2025 | Mar 19, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 18, 2025 | May 8, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 5, 2025 | May 5, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 12, 2025 | Jun 12, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 2, 2025 | Jul 2, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Jul 2, 2025 | Jul 3, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2025 | Aug 4, 2025 | Administrative |
Addendum 1: Final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2025 | Dec 30, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Dec 15, 2025 | Jan 20, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jan 5, 2026 | Jan 16, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 20, 2026 | Jan 23, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 20, 2026 | Mar 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 20, 2026 | Mar 3, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 20, 2026 | Feb 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 20, 2026 | May 15, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 20, 2026 | Jan 26, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 20, 2026 | Jan 22, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jan 20, 2026 | Jan 29, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 20, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2026 | Jan 22, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 20, 2026 | Feb 26, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | May 28, 2026 | May 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2026 | Jun 30, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 1, 2026 | Jun 1, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 2, 2026 | Jun 4, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2026 | Jun 5, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 10, 2026 | Jun 11, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 2, 2026 | Sep 18, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 10, 2026 | Oct 13, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 18, 2026 | Sep 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2026 | Sep 25, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 29, 2026 | Sep 29, 2026 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Oct 15, 2026 | Oct 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 26, 2026 | Oct 28, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 29, 2026 | Oct 30, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 29, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 29, 2026 | Oct 30, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 29, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $2,282,050
| Name | Role | License on permit |
|---|---|---|
| Jeremiah W P Schaub Schaub | Li | Architects | Architect | C-32289 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025