2639 21st Av

San Francisco permit 202308285406 · Sunset/Parkside

ADUFull plan reviewComplete
Street view · Nov 2013
Google Street View of 2639 21st Av, Nov 2013
Scope of work
As written on the permit application.

Legalize existing conditioned space as a 1-bedroom accessory dwelling unit(adu). 382 sq ft. per ordinace 95-17

Timeline
Key dates from the city record.
Filed
Aug 28, 2023
Issued
Apr 19, 2024 (8 months after filing)
Completed
Nov 24, 2025 (19 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
48 stops across 6 departments
Comments issued
11 times, by Building Inspection, Public Works

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 13, 2023Administrative

Zoning review

Planning · CP-ZOC

Sep 27, 2023Approved

Building plan review

Building Inspection · BLDG

Sep 26, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Sep 22, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 14, 2023Approved

Urban forestry

Public Works · DPW-BUF

Oct 2, 2023Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Sep 15, 2023Approved

Permit Processing Center

Building Inspection · PPC

Apr 1, 2024Administrative

Building plan review

Building Inspection · BLDG

Nov 2, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Feb 2, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 2, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 12, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 18, 2024Approved

Zoning review

Planning · CP-ZOC

Mar 21, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 26, 2024Approved

Urban forestry

Public Works · DPW-BUF

Mar 29, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 25, 2024Approved

Development fee collection

Building Inspection · DFCU

Apr 1, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Apr 19, 2024Administrative

Addendum 1: Arch structurl mep final

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 14, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

May 7, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

May 8, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

May 13, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

May 14, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 15, 2024Administrative

Building plan review

Building Inspection · BLDG

Jun 6, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 11, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 21, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 10, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 24, 2024Approved

Urban forestry

Public Works · DPW-BUF

Jun 7, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 17, 2024Approved

Permit Processing Center

Building Inspection · PPC

Sep 16, 2024Administrative

Building plan review quality control

Building Inspection · BLDG-QC

Jun 5, 2024Administrative

Urban forestry

Public Works · DPW-BUF

Jun 28, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 16, 2024Administrative

Building plan review

Building Inspection · BLDG

Aug 9, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 15, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 7, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Aug 16, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Aug 19, 2024Approved

Fire prevention review

Fire Department · SFFD

Aug 20, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 19, 2024Approved

Urban forestry

Public Works · DPW-BUF

Sep 13, 2024Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Aug 29, 2024Approved

Urban forestry

Public Works · DPW-BUF

Sep 13, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 18, 2024Administrative

Development fee collection

Building Inspection · DFCU

Sep 18, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$60,571
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Sam Tsui

Tas Consulting Engineers

EngineerC78233
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202308285406 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record