742 26th Av
San Francisco permit 202308285460 · Outer Richmond
Vert+horz addition & remodel. add adu w/2 bdrms & 2 baths at 1st flr. full remodel of 2nd flr+add 2 bdrms and 2 baths. new 3rd flr to include 3 baths 3 bdrms and 1 kitchen. (n) 3rd flr exterior facade to match existing. new rear balconies.
- Filed
- Aug 28, 2023
- Issued
- Dec 5, 2024 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 59 stops across 6 departments
- Comments issued
- 18 times, by Public Works, Public Utilities, Building Inspection, Planning, Permit Center
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 28, 2023 | Aug 28, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 21, 2023 | Sep 29, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 29, 2023 | May 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 29, 2023 | Sep 11, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 16, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 6, 2024 | May 14, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | May 6, 2024 | May 21, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2024 | May 6, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2024 | May 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 16, 2024 | May 20, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 20, 2024 | May 20, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 20, 2024 | Jun 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 9, 2024 | Jul 9, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 12, 2024 | Jul 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 16, 2024 | Jul 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2024 | Jul 17, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 17, 2024 | Jul 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 25, 2024 | Jul 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 25, 2024 | Aug 16, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 16, 2024 | Sep 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 11, 2024 | Dec 5, 2024 | Administrative |
Addendum 1: Final - foundation, superstructure, mechanical, t-24, electrical.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 6, 2024 | Dec 20, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 17, 2025 | Feb 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 18, 2025 | Feb 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 19, 2025 | Feb 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 19, 2025 | Mar 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 19, 2025 | Mar 7, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 19, 2025 | Mar 6, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 19, 2025 | Feb 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 19, 2025 | Feb 19, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 19, 2025 | Mar 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 19, 2025 | Mar 3, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 19, 2025 | Sep 10, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2025 | Mar 24, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 13, 2025 | Jul 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 13, 2025 | Jun 20, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 13, 2025 | Jun 16, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 13, 2025 | Jul 8, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 13, 2025 | Jun 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 13, 2025 | Jun 16, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 13, 2025 | Jul 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 13, 2025 | Jun 25, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 23, 2025 | Jun 24, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 15, 2025 | Jul 18, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 15, 2025 | Aug 11, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2025 | Jul 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 15, 2025 | Jul 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2025 | Jul 16, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 15, 2025 | Aug 8, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2025 | Jul 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 29, 2025 | Sep 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 29, 2025 | Sep 4, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 29, 2025 | Sep 2, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 29, 2025 | Sep 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 29, 2025 | Sep 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2025 | Sep 3, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 29, 2025 | Sep 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 29, 2025 | Sep 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2025 | Dec 23, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,310,000
| Name | Role | License on permit |
|---|---|---|
| Geddes J Ulinskas Geddes Ulinskas Arch. | Architect | C-27862 |
| Ronald Gate Yu Yuflux Engineering Llc. | Engineer | C76647 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2019