420 23rd St
San Francisco permit 202308305599 · Potrero Hill
Select demolition includes removal of selected concrete walls to create (n) openins thru (e) concrete turbine platform.
- Filed
- Aug 30, 2023
- Issued
- Sep 14, 2023 (within 1 month of filing)
- Completed
- Oct 31, 2024 (14 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 5 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 30, 2023 | Aug 30, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 7, 2023 | Sep 7, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2023 | Sep 8, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 8, 2023 | Sep 8, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 14, 2023 | Sep 14, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Paul Anthony Littler Holmes Structural | Engineer | S6189 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026