4 Embarcadero Center
San Francisco permit 202308305620 · Financial District/South Beach
Suite 101: demolition of (e) casework and booths, new bar casework, new partition walls, new all infill, new butler door, new light fixtures and new bar and handwash sinks. patch and repair of (e) floor tiles, new paint finish
- Filed
- Aug 30, 2023
- Issued
- Jan 11, 2024 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 16 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Public Health, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 30, 2023 | Aug 30, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 30, 2023 | Aug 30, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 6, 2023 | Sep 6, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Sep 6, 2023 | Sep 6, 2023 | Administrative |
Public health review Public Health · HEALTH | Sep 6, 2023 | Sep 8, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 19, 2023 | Dec 19, 2023 | Approved |
Public health review Public Health · HEALTH | Dec 19, 2023 | Dec 19, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 20, 2023 | Dec 20, 2023 | Issued Comments |
Intake Building Inspection · INTAKE | Dec 21, 2023 | Dec 21, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 21, 2023 | Dec 21, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Dec 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 21, 2023 | Dec 21, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 21, 2023 | Dec 21, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 21, 2023 | Dec 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 10, 2024 | Jan 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 11, 2024 | Jan 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Anne Marie Cervantes | Architect | C18037 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2017