In respose to 2022-011286enf enforcement by planning dept. to legalize unauthorized dwelling unit at 1st fl. legalize unpermitted structure due to removal of the (e) beam and post on the 1st fl. front facade remain no change.

Timeline
Key dates from the city record.
Filed
Aug 31, 2023
Issued
Jul 5, 2024 (10 months after filing)
Completed
Mar 20, 2026 (20 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 5 departments
Comments issued
6 times, by Planning, Building Inspection, Public Works, Fire Department
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 6, 2023Administrative

Zoning review

Planning · CP-ZOC

Oct 11, 2023Issued Comments

Permit Processing Center

Building Inspection · PPC

Jun 3, 2024Administrative

Zoning review

Planning · CP-ZOC

Nov 28, 2023Approved

Zoning review

Planning · CP-ZOC

Nov 28, 2023Administrative

Building plan review

Building Inspection · BLDG

Jan 25, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 10, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Dec 4, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 11, 2023Approved

Urban forestry

Public Works · DPW-BUF

May 20, 2024Approved

Fire prevention review

Fire Department · SFFD

Feb 13, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Mar 28, 2024Administrative

Building plan review

Building Inspection · BLDG

Apr 15, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 20, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 19, 2024Approved

Zoning review

Planning · CP-ZOC

Mar 20, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 27, 2024Approved

Building plan review quality control

Building Inspection · BLDG-QC

Apr 15, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

May 9, 2024Approved

Street use and mapping

Public Works · DPW-BSM

May 8, 2024Approved

Fire prevention review

Fire Department · SFFD

May 14, 2024Approved

Zoning review

Planning · CP-ZOC

May 21, 2024Approved

Building plan review

Building Inspection · BLDG

May 21, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 3, 2024Approved

Fire prevention review

Fire Department · SFFD

May 21, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 21, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jul 5, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$200,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Junjian Lao

Lao Engineering

EngineerC82114
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202308315692 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record