2258 34th Av
San Francisco permit 202308315692 · Sunset/Parkside
In respose to 2022-011286enf enforcement by planning dept. to legalize unauthorized dwelling unit at 1st fl. legalize unpermitted structure due to removal of the (e) beam and post on the 1st fl. front facade remain no change.
- Filed
- Aug 31, 2023
- Issued
- Jul 5, 2024 (10 months after filing)
- Completed
- Mar 20, 2026 (20 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 27 stops across 5 departments
- Comments issued
- 6 times, by Planning, Building Inspection, Public Works, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 31, 2023 | Sep 6, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 6, 2023 | Oct 11, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 6, 2023 | Jun 3, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 28, 2023 | Nov 28, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 28, 2023 | Nov 28, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 28, 2023 | Jan 25, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 28, 2023 | Jan 10, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 28, 2023 | Dec 4, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 28, 2023 | Dec 11, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 6, 2023 | May 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 5, 2024 | Feb 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 11, 2024 | Mar 28, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 11, 2024 | Apr 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2024 | Mar 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2024 | Mar 19, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 20, 2024 | Mar 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 26, 2024 | Mar 27, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 15, 2024 | Apr 15, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 23, 2024 | May 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2024 | May 8, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 14, 2024 | May 14, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 21, 2024 | May 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2024 | May 21, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 21, 2024 | Jun 3, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 21, 2024 | May 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2024 | May 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2024 | Jul 5, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Junjian Lao Lao Engineering | Engineer | C82114 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022