1912 09th Av
San Francisco permit 202309066000 · Inner Sunset
Removal of(e)flat roof over 2-story bldg envelope @ rear, select interior walls(e) single glazed windoes & doors @conditioned space.replace in-kind flat roof in rear yard setback (no increase in bldg envelope) & (n) shed and flat roof over
- Filed
- Sep 6, 2023
- Issued
- Feb 20, 2024 (5 months after filing)
- Completed
- Jun 25, 2026 (28 months after issuance)
- Review stops
- 38 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 6, 2023 | Sep 7, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 7, 2023 | Jan 18, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 7, 2023 | Feb 9, 2024 | — |
Planning neighborhood notice Planning · CP-NP | Nov 14, 2023 | Nov 21, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Jan 18, 2024 | Feb 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 18, 2024 | Feb 7, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 18, 2024 | Jan 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 9, 2024 | Feb 20, 2024 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 14, 2024 | Mar 22, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 21, 2024 | Mar 21, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 21, 2024 | Mar 21, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 21, 2024 | Mar 21, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 21, 2024 | Mar 21, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Mar 22, 2024 | Mar 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 22, 2024 | May 17, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 22, 2024 | Apr 11, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2024 | Apr 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2024 | Mar 25, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 22, 2024 | Jul 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 17, 2024 | May 20, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 28, 2025 | Jul 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2025 | Feb 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 28, 2025 | Feb 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 28, 2025 | Jan 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2025 | Feb 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 21, 2025 | Feb 26, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 21, 2025 | Mar 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 21, 2025 | Feb 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 21, 2025 | Mar 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 25, 2025 | Jul 8, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2025 | Jul 11, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2025 | Jul 1, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2025 | Jul 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 15, 2025 | Jul 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2025 | Jul 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2025 | Jul 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2025 | Jul 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2025 | Aug 4, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Ross Harlen Levy Levy Art & Architecture | Architect | C25660 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025