903 Grant Av
San Francisco permit 202309066021 · Chinatown
To comply w/ the abe program abe# 202308028091. requesting a technical infeasibility due to lack to space to modify (e) steps at store entrance to become a ada ramp. install power door operator.
- Filed
- Sep 6, 2023
- Issued
- Oct 19, 2023 (1 month after filing)
- Completed
- Dec 15, 2023 (2 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 6 stops across 2 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Sep 6, 2023 | Sep 6, 2023 | Administrative |
Intake Building Inspection · INTAKE | Sep 6, 2023 | Sep 6, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 6, 2023 | Sep 6, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 6, 2023 | Sep 6, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 13, 2023 | Sep 13, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 19, 2023 | Oct 19, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $3,500
| Name | Role | License on permit |
|---|---|---|
| Lok Cheung Kwan | Engineer | 1836 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2018