2565 03rd St
San Francisco permit 202309076103 · Potrero Hill
Verizon install (9)(n) antennas (3) sectors, (12)(n) radio units in (3) sectors, all sectors will be screened by frp to match bldg, (4)(n) surge suppressors, (1) meter panel in (e) electrical rm, (1) step down transformer, 1 ppc distribution panel, 3 (n) hybrid cables 1 per sector, 1 gen plug, 1 gps
- Filed
- Sep 7, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 19 stops across 5 departments
- Comments issued
- 5 times, by Planning, Building Inspection, Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 7, 2023 | Sep 7, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 7, 2023 | Sep 7, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 13, 2023 | Sep 13, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 13, 2023 | Sep 13, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Sep 13, 2023 | Sep 13, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Sep 14, 2023 | Sep 20, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 21, 2023 | Oct 24, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 24, 2023 | Oct 30, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 30, 2023 | Nov 15, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Nov 15, 2023 | Nov 15, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Nov 29, 2023 | Nov 29, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 29, 2023 | Dec 29, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 20, 2024 | Feb 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 4, 2024 | Mar 4, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 4, 2024 | Mar 6, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 6, 2024 | Mar 13, 2024 | Approved |
Public health review Public Health · HEALTH | Mar 18, 2024 | Mar 20, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 21, 2024 | Mar 21, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2024 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $330,000
| Name | Role | License on permit |
|---|---|---|
| Eric Kirk Uhrenholt Diamond Engineering Services | Engineer | C59712 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025