As written on the permit application.

Response to sf planning notice of violation (#2021-007096enf). consolidate previously issued permits (#2012-0104-1711, 2012-0518-0809, 2012-0911-9462, 2016-809-4586, 2017-1107-3317 & 2018-0320-4094)as well as legalize additional un-permitted work done by previous owner(s),

Timeline
Key dates from the city record.
Filed
Sep 7, 2023
Issued
Oct 30, 2026 (38 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 5 departments
Comments issued
7 times, by Planning, Fire Department, Building Inspection, Public Utilities
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 8, 2023Administrative

Zoning review

Planning · CP-ZOC

Feb 1, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Aug 13, 2026Administrative

Building plan review

Building Inspection · BLDG

Nov 19, 2024Administrative

Fire prevention review

Fire Department · SFFD

Jul 22, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 1, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 15, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 30, 2024Issued Comments

Mechanical plan review quality control

Building Inspection · MECH-QC

Aug 1, 2024Administrative

Zoning review

Planning · CP-ZOC

Jun 25, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 25, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 19, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 20, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 18, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 10, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 12, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 10, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Apr 23, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 30, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 7, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 29, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Jul 10, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 26, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Oct 30, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$571,663
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Paul J Haydu

Jones/Haydu-Designer

ArchitectC32366
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202309076134 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record