Response to sf planning notice of violation (#2021-007096enf). consolidate previously issued permits (#2012-0104-1711, 2012-0518-0809, 2012-0911-9462, 2016-809-4586, 2017-1107-3317 & 2018-0320-4094)as well as legalize additional un-permitted work done by previous owner(s),
- Filed
- Sep 7, 2023
- Issued
- Oct 30, 2026 (38 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 7 times, by Planning, Fire Department, Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 7, 2023 | Sep 8, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 8, 2023 | Feb 1, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 8, 2023 | Aug 13, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 8, 2024 | Nov 19, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 10, 2024 | Jul 22, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2024 | Aug 1, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 12, 2024 | Jul 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2024 | Jul 30, 2024 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Aug 1, 2024 | Aug 1, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 15, 2024 | Jun 25, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 15, 2024 | Nov 25, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 15, 2024 | Nov 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 15, 2024 | Nov 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 15, 2024 | Nov 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 19, 2024 | Feb 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2024 | Dec 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2025 | Feb 10, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 23, 2025 | Apr 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 25, 2026 | Jun 30, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2026 | Jul 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 25, 2026 | Jun 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2026 | Jul 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2026 | Jun 26, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 13, 2026 | Oct 30, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $571,663
| Name | Role | License on permit |
|---|---|---|
| Paul J Haydu Jones/Haydu-Designer | Architect | C32366 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022