121 Hancock St #0
San Francisco permit 202309086148 · Castro/Upper Market
Remove section of gabled roof at rear of third floor to create three dormers per 2a3 for upper unit within buildable area
- Filed
- Sep 8, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 14 stops across 4 departments
- Comments issued
- 4 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building pre-screening Building Inspection · PRE-BLDG | Sep 11, 2023 | Sep 11, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 11, 2023 | Sep 19, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 21, 2023 | Nov 22, 2023 | Issued Comments |
Planning neighborhood notice Planning · CP-NP | Feb 15, 2024 | Feb 22, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 30, 2024 | May 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 3, 2024 | Jul 22, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Jun 20, 2024 | Jun 20, 2024 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Jul 22, 2024 | Jul 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 24, 2024 | Jul 31, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 13, 2024 | Aug 14, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $145,000
| Name | Role | License on permit |
|---|---|---|
| Mark Reilly Mark Reilly Architecture | Architect | C-33112 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026