CheckMyDesigner

253 States St

San Francisco permit 202309086209 · Castro/Upper Market

Revision or supplementFull plan reviewIssued

This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.

Street view · Jan 2023
Google Street View of 253 States St, Jan 2023
Scope of work
As written on the permit application.

Revision to pa# 202305047077. relocate kitchen. remove (e) water heater & install (n) tankless water heater. install (n) bath at ground level. 25 c/y excavation. lower slab 2". new foundation.

Timeline
Key dates from the city record.
Filed
Sep 8, 2023
Issued
Feb 22, 2024 (5 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
18 stops across 5 departments
Comments issued
3 times, by Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Sep 8, 2023Administrative

Zoning review

Planning · CP-ZOC

Sep 8, 2023Approved

Permit Center

Permit Center · PERMIT-CTR

Sep 8, 2023—

Central Permit Bureau

Building Inspection · CPB

Sep 20, 2023Administrative

Building plan review

Building Inspection · BLDG

Oct 10, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 23, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 28, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Nov 30, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 11, 2023Approved

Building plan review

Building Inspection · BLDG

Dec 19, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Jan 8, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Jan 9, 2024Approved

Zoning review

Planning · CP-ZOC

Jan 9, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 11, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jan 12, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 19, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jan 22, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Feb 22, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$121,918
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Ehsan Yazdan Panah

Aexsf Llc

EngineerS7067
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202309086209 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record