1328 York St
San Francisco permit 202309116348 · Mission
Add a new garage (665sf +/-) and replace brick foundation to concrete foundation.
- Filed
- Sep 11, 2023
- Issued
- Oct 3, 2024 (13 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 43 stops across 6 departments
- Comments issued
- 11 times, by Public Works, Public Utilities, Building Inspection
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 11, 2023 | Oct 5, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 5, 2023 | Feb 13, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 5, 2023 | Sep 4, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 13, 2024 | Feb 27, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2024 | Mar 14, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 13, 2024 | Mar 18, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2024 | Feb 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2024 | Mar 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2024 | Jul 15, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Jul 15, 2024 | Jul 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 15, 2024 | Jul 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2024 | Jul 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 23, 2024 | Aug 20, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 3, 2024 | Sep 3, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Sep 3, 2024 | Sep 3, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2024 | Oct 3, 2024 | Administrative |
Addendum 1: Arch / foundation / structural.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 10, 2025 | Jan 14, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2025 | Jul 11, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | May 27, 2025 | Jun 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 11, 2025 | Jul 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2025 | Aug 21, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 11, 2025 | Aug 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2025 | Aug 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 11, 2025 | Aug 13, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2025 | Jul 14, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 11, 2025 | Jul 18, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 11, 2025 | Jul 18, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 11, 2025 | Jan 7, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Oct 6, 2025 | Oct 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 6, 2025 | Oct 14, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 6, 2025 | Oct 14, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2025 | Oct 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 6, 2025 | Oct 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 6, 2025 | Oct 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 6, 2025 | Oct 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 3, 2025 | Dec 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 3, 2025 | Dec 8, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 3, 2025 | Dec 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 3, 2025 | Dec 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2025 | Dec 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 3, 2025 | Dec 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 3, 2025 | Dec 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 7, 2026 | Mar 19, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Charles C Chan Cc Architects Inc. | Architect | C31716 |
| Edmond Wong Ekw Engineering | Engineer | C86522 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026