2300 Harrison St
San Francisco permit 202309126396 · Mission
Roof deck to be enlarged & enhancced. increase the perimeter of deck by 4' along 3 sides, reconfigure the ramp system to be compliant w/accessibility
- Filed
- Sep 12, 2023
- Issued
- Jan 11, 2024 (4 months after filing)
- Completed
- Oct 16, 2024 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 18 stops across 2 departments
- Comments issued
- 8 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 12, 2023 | Sep 12, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 12, 2023 | Sep 12, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 13, 2023 | Sep 13, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 13, 2023 | Sep 13, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 26, 2023 | Sep 26, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 19, 2023 | Oct 19, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 19, 2023 | Oct 19, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 19, 2023 | Oct 19, 2023 | Administrative |
Intake Building Inspection · INTAKE | Oct 20, 2023 | Oct 20, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2023 | Oct 24, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 20, 2023 | Oct 20, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Dec 15, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 4, 2024 | Jan 4, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 5, 2024 | Jan 5, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 5, 2024 | Jan 5, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 9, 2024 | Jan 9, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Jan 9, 2024 | Jan 10, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 10, 2024 | Jan 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Marc Andrew Steyer Tipping Structural Engineers | Engineer | S6022 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026