737 Pine St #0
San Francisco permit 202309196934 · Nob Hill
Concrete repair of slab & beams @ lower garage ceiling, form 8 to form 3 conversion, p. chan reviewed/commented at counter, dmj 10/13/2023;
- Filed
- Sep 19, 2023
- Issued
- Dec 12, 2023 (3 months after filing)
- Completed
- Apr 9, 2024 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 15 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Sep 19, 2023 | Sep 19, 2023 | Administrative |
Building inspector Building Inspection · BID-INSP | Sep 19, 2023 | Sep 19, 2023 | Approved |
Intake Building Inspection · INTAKE | Sep 19, 2023 | Sep 19, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 20, 2023 | Sep 20, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 25, 2023 | Sep 25, 2023 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2023 | Oct 13, 2023 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Oct 10, 2023 | Oct 10, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | Oct 13, 2023 | Oct 13, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2023 | Nov 17, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 20, 2023 | Nov 21, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 21, 2023 | Nov 27, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 28, 2023 | Nov 28, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 28, 2023 | Nov 30, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 4, 2023 | Dec 4, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 4, 2023 | Dec 12, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Behruz Vahdani-Sanavi Us Prime Contractor Inc. | Engineer | C35605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026