142 Alpine Tr
San Francisco permit 202309206980 · Castro/Upper Market
Additional dwelling unit (adu) at first floor.
- Filed
- Sep 20, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 35 stops across 6 departments
- Comments issued
- 17 times, by Permit Center, Building Inspection, Planning, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 27, 2024 | Sep 10, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 3, 2024 | Sep 3, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 5, 2024 | Sep 5, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 5, 2024 | Sep 5, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Sep 10, 2024 | Sep 24, 2024 | Issued Comments |
Building inspector Building Inspection · BID-INSP | Sep 12, 2024 | Sep 12, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 13, 2024 | Sep 13, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 20, 2024 | Sep 20, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 20, 2024 | Dec 9, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Nov 26, 2024 | Nov 26, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 26, 2024 | Nov 26, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Dec 9, 2024 | Dec 9, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Dec 9, 2024 | Dec 9, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 3, 2025 | Jan 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 14, 2026 | Feb 10, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 14, 2026 | Mar 4, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 14, 2026 | Feb 18, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2026 | Jan 30, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jan 14, 2026 | Jan 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 14, 2026 | Jan 22, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 14, 2026 | Feb 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 14, 2026 | Jan 27, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 14, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2026 | Jan 21, 2026 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Feb 4, 2026 | Feb 4, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 2, 2026 | Mar 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2026 | May 21, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filing
- Estimated cost
- $25,000
| Name | Role | License on permit |
|---|---|---|
| Philip Whitehead Whitehead & Assoc. | Engineer | C30996 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025