967 Mission St
San Francisco permit 202309227225 · South of Market
Mayoral ed 13-01 priority process ab004 - erect 9-story residential apartment building, 95 dwelling units with no basement,type 1a.
- Filed
- Sep 22, 2023
- Issued
- Aug 19, 2024 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 169 stops across 7 departments
- Comments issued
- 41 times, by Building Inspection, Fire Department, Public Utilities, Permit Center, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 22, 2023 | Sep 25, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Sep 25, 2023 | Jan 31, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 25, 2023 | Aug 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Jan 4, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 21, 2023 | Dec 21, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 21, 2023 | Dec 21, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 21, 2023 | Jan 10, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Dec 21, 2023 | Jan 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 21, 2023 | Dec 28, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 5, 2024 | Jan 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 2, 2024 | Feb 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 2, 2024 | Feb 8, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 2, 2024 | Feb 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 2, 2024 | Feb 16, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Feb 2, 2024 | Apr 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2024 | Feb 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Feb 28, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 27, 2024 | Feb 27, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2024 | Feb 28, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2024 | Feb 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 29, 2024 | Feb 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 22, 2024 | Mar 26, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 22, 2024 | Mar 25, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 22, 2024 | Mar 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2024 | Mar 25, 2024 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2024 | Mar 25, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2024 | Mar 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 26, 2024 | Mar 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 3, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 2, 2024 | Apr 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2024 | Apr 8, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 2, 2024 | Apr 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 2, 2024 | Apr 11, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Apr 18, 2024 | Apr 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 2, 2024 | Aug 2, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Aug 2, 2024 | Aug 13, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 15, 2024 | Aug 19, 2024 | Administrative |
Addendum 1: Foundation, superstructure, civil
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 20, 2024 | Aug 30, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 21, 2024 | Sep 3, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 27, 2024 | Aug 27, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 29, 2024 | Aug 29, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Aug 30, 2024 | Aug 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 3, 2024 | Oct 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 3, 2024 | Sep 4, 2024 | Approved |
CON CON-BOND | Sep 3, 2024 | Sep 26, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 3, 2024 | Apr 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 16, 2024 | Oct 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 20, 2024 | Jan 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2024 | Feb 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 20, 2025 | Feb 20, 2025 | Issued Comments |
Development fee collection Building Inspection · DFCU | Feb 21, 2025 | Feb 21, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 27, 2025 | Feb 28, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 7, 2025 | Mar 13, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2025 | Mar 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 17, 2025 | Mar 17, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 19, 2025 | Mar 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2025 | Apr 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 14, 2025 | Oct 27, 2025 | Administrative |
Addendum 2: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 6, 2025 | Aug 20, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2025 | Feb 6, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jan 21, 2026 | Feb 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 6, 2026 | Feb 18, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 6, 2026 | Feb 18, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Feb 6, 2026 | Feb 11, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2026 | Feb 12, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 6, 2026 | May 29, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 4, 2026 | May 5, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 4, 2026 | May 4, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | May 4, 2026 | May 5, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 4, 2026 | May 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 29, 2026 | May 29, 2026 | Administrative |
Addendum 3: Architectural / mep including landscaping
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 20, 2024 | Sep 4, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 27, 2024 | Aug 27, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 29, 2024 | Aug 29, 2024 | Approved-Stipulated |
Building pre-screening Building Inspection · PRE-BLDG | Aug 30, 2024 | Aug 30, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 12, 2024 | Sep 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 17, 2024 | Sep 17, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 20, 2024 | Sep 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 25, 2024 | Sep 25, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 25, 2024 | Sep 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 25, 2024 | Nov 6, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2024 | Oct 21, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 25, 2024 | Oct 18, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 25, 2024 | Oct 23, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2024 | Sep 25, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 25, 2024 | Sep 27, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 25, 2024 | Apr 24, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 5, 2024 | Nov 5, 2024 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Nov 5, 2024 | Nov 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 20, 2024 | Dec 31, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2024 | Jan 7, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 20, 2024 | Dec 20, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 20, 2024 | Dec 24, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2024 | Dec 23, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 20, 2024 | Dec 31, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2024 | Dec 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 17, 2025 | Jan 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 17, 2025 | Feb 5, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 17, 2025 | Jan 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 17, 2025 | Jan 21, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 17, 2025 | Jan 23, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 17, 2025 | Jan 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 17, 2025 | Jan 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2025 | Feb 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 7, 2025 | Mar 10, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 7, 2025 | Mar 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 7, 2025 | Mar 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 7, 2025 | Mar 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 7, 2025 | Mar 21, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2025 | Mar 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 7, 2025 | Mar 10, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 19, 2025 | Mar 20, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 19, 2025 | Mar 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2025 | Mar 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 19, 2025 | Mar 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2025 | Mar 20, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2025 | Mar 21, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 14, 2025 | Apr 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2025 | Oct 27, 2025 | Administrative |
Addendum 4: Fire sprinkler and underground
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 13, 2025 | Nov 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 14, 2025 | Nov 20, 2025 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Nov 20, 2025 | Dec 2, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2025 | Dec 1, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 20, 2025 | Jan 15, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Jan 13, 2026 | Jan 14, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2026 | Jan 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 15, 2026 | Jan 16, 2026 | Administrative |
Addendum 6: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 10, 2026 | Apr 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2026 | Apr 22, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 22, 2026 | Jun 17, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Apr 22, 2026 | May 15, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | Apr 22, 2026 | Apr 30, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 22, 2026 | Jun 26, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 25, 2026 | Jun 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 26, 2026 | Jun 26, 2026 | Administrative |
Addendum 7: Fire alarm, elevator landing and two-way communication
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 28, 2026 | Nov 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 2, 2026 | Nov 4, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Nov 4, 2026 | In progress | — |
Permit Processing Center Building Inspection · PPC | Nov 4, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 8: Errcs - emergency responder radio coverage system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 28, 2026 | Nov 4, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 4, 2026 | Nov 4, 2026 | Administrative |
Address verification Building Inspection · ADDR | Nov 4, 2026 | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | Nov 4, 2026 | In progress | — |
Permit Processing Center Building Inspection · PPC | Nov 4, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 10: Solar pv
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 14, 2026 | Oct 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2026 | Oct 27, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Oct 27, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Oct 27, 2026 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Oct 27, 2026 | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | Oct 27, 2026 | Oct 29, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 27, 2026 | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 13: Ground improvement/drill displacement
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 28, 2026 | May 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 7, 2026 | May 7, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 7, 2026 | May 14, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 7, 2026 | May 14, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | May 7, 2026 | May 15, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 7, 2026 | May 18, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 7, 2026 | Jul 23, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 2, 2026 | Jun 6, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jun 2, 2026 | Jun 9, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Jun 2, 2026 | Jun 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 10, 2026 | Jul 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2026 | Jul 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 23, 2026 | Jul 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2026 | Jul 27, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $61,000,000
| Name | Role | License on permit |
|---|---|---|
| Jason J. Ling Urban Design Consulting Eng | Engineer | C60493 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2016