988 Market St #1
San Francisco permit 202309257314 · Tenderloin
Conversion of existing office space into residential units with-in a historical building. with no modifications to the exterior or height of the building.
- Filed
- Sep 25, 2023
- Issued
- Oct 31, 2023 (1 month after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 16 stops across 6 departments
- Comments issued
- Twice, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 25, 2023 | Oct 3, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 3, 2023 | Oct 4, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 3, 2023 | Oct 4, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 3, 2023 | Oct 5, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 3, 2023 | Oct 4, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2023 | Oct 6, 2023 | Approved |
Public health review Public Health · HEALTH | Oct 3, 2023 | Oct 4, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Oct 3, 2023 | Oct 25, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Oct 24, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 24, 2023 | Oct 25, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 24, 2023 | Oct 24, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2023 | Oct 24, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 24, 2023 | Oct 24, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 24, 2023 | Oct 24, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Oct 24, 2023 | Oct 24, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 25, 2023 | Oct 31, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $9,500,000
| Name | Role | License on permit |
|---|---|---|
| Craig Brian Scott Craig Iwamotto Scott | Architect | C23713 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026