Enlarge 3rd floor bedroom & add bathroom by raising (e) roofline. new construction to cover (e) lightwell at 2nd floor. no change in building footprint of overall building height.

Timeline
Key dates from the city record.
Filed
Sep 28, 2023
Issued
Jul 3, 2024 (9 months after filing)
Completed
May 19, 2025 (11 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
14 stops across 4 departments
Comments issued
4 times, by Building Inspection, Public Works, Public Utilities
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 28, 2023Administrative

Zoning review

Planning · CP-ZOC

Feb 29, 2024Approved

Planning neighborhood notice

Planning · CP-NP

Jan 10, 2024Administrative

Building plan review

Building Inspection · BLDG

Apr 16, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 1, 2024Issued Comments

Mechanical plan review quality control

Building Inspection · MECH-QC

May 1, 2024Administrative

Street use and mapping

Public Works · DPW-BSM

May 9, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 17, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 30, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 13, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 17, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 24, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jun 25, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Jul 3, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$90,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Gary Wayne Meyer

Waynemeyerworks

ArchitectC-31705
Kathryn Briggs

Base Design

Engineer5732
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202309287573 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record