1278 Minnesota St
San Francisco permit 202309297767 · Potrero Hill
Change of use. level 1 & 2: renovation of (e) workshop space into community facility, mep deferred.
- Filed
- Sep 29, 2023
- Issued
- Mar 12, 2024 (5 months after filing)
- Completed
- Jun 14, 2024 (3 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 15 stops across 4 departments
- Comments issued
- 6 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Sep 29, 2023 | Sep 29, 2023 | — |
Intake Building Inspection · INTAKE | Sep 29, 2023 | Sep 29, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 2, 2023 | Oct 2, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 11, 2023 | Oct 11, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2023 | Oct 11, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 12, 2023 | Oct 12, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 13, 2023 | Oct 13, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 16, 2023 | Oct 16, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 28, 2023 | Nov 28, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Nov 29, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 7, 2024 | Mar 7, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 8, 2024 | Mar 8, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 8, 2024 | Mar 8, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 12, 2024 | Mar 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2024 | Mar 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $650,000
| Name | Role | License on permit |
|---|---|---|
| Maryam Farnaz Rostami Tef Design | Architect | C37717 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026