1800 Owens St
San Francisco permit 202310037923 · Potrero Hill
New condenser water unit & new vfd's on sector 1 roof with associated structural support. chilled water piping from new condenser unit will run in an existing shaft down to level 1. no architectural work proposed. all work is mep w/ structural.
- Filed
- Oct 3, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 12 stops across 6 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 3, 2023 | Oct 3, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 4, 2023 | Oct 4, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 4, 2023 | Oct 4, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 5, 2023 | Oct 5, 2023 | Administrative |
Public health review Public Health · HEALTH | Oct 5, 2023 | Oct 5, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Jan 10, 2024 | Jan 10, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 10, 2024 | Jan 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2024 | Jan 12, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jan 12, 2024 | Jan 12, 2024 | Administrative |
Redevelopment review Redevelopment · REDEV | Jan 12, 2024 | Jan 16, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jan 17, 2024 | Jan 17, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Randall Robert Dowler Dowler Gruman Architects | Architect | C23107 |
| Geoffrey Daniel Bomba | Engineer | S5455 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026