3318 Steiner St
San Francisco permit 202310047992 · Marina
Cold shell building for future restaurant build-out: facade renovation including moment frame, new restroom, new roof and skylight, seismic upgrade, new floor slab, new electrical service, new plumbing service. deferred electrical & mep permits.
- Filed
- Jun 18, 2024
- Issued
- Mar 21, 2025 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 43 stops across 7 departments
- Comments issued
- 12 times, by Permit Center, Building Inspection, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 4, 2023 | Oct 4, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 4, 2023 | Apr 12, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 12, 2024 | Apr 12, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 17, 2024 | Apr 17, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Apr 24, 2024 | May 7, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 29, 2024 | Apr 29, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Apr 30, 2024 | Apr 30, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 30, 2024 | Apr 30, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 9, 2024 | May 23, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 16, 2024 | May 16, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | May 20, 2024 | May 20, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 22, 2024 | May 22, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 4, 2024 | Jun 12, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 12, 2024 | Jun 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 18, 2024 | Jun 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jun 20, 2024 | Oct 31, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 20, 2024 | Jul 19, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 20, 2024 | Aug 9, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 20, 2024 | Jul 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 20, 2024 | Aug 5, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2024 | Jul 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 20, 2024 | Jul 3, 2024 | Approved |
Public health review Public Health · HEALTH | Jun 20, 2024 | Sep 3, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 20, 2024 | Nov 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jun 26, 2024 | Jun 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 13, 2024 | Aug 13, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 14, 2024 | Aug 14, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 27, 2024 | Aug 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2024 | Sep 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 20, 2024 | Oct 11, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 23, 2024 | Sep 23, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2024 | Sep 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 25, 2024 | Sep 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 11, 2024 | Oct 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 14, 2024 | Oct 23, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 22, 2024 | Oct 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 23, 2024 | Oct 23, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 24, 2024 | Oct 24, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2024 | Oct 24, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2024 | Nov 15, 2024 | Approved |
Public health review Public Health · HEALTH | Oct 31, 2024 | Nov 4, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 31, 2024 | Nov 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2024 | Mar 21, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $431,983
| Name | Role | License on permit |
|---|---|---|
| Andrew Joseph Carpentier Studio T Square | Architect | C-17255 |
| David Michael Mcmillan | Engineer | S-5988 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026