100 California St
San Francisco permit 202310058107 · Financial District/South Beach
Switchgear replacement project that includes a new base building main electrical room within an (e) exercise room & limited accessibility upgrades to the restrooms serving the area of remodel.
- Filed
- Oct 5, 2023
- Issued
- Dec 14, 2023 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 5, 2023 | Oct 5, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Oct 5, 2023 | Oct 5, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 5, 2023 | Oct 5, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 5, 2023 | Oct 5, 2023 | — |
Fire prevention review Fire Department · SFFD | Oct 5, 2023 | Oct 5, 2023 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Oct 20, 2023 | Oct 20, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 20, 2023 | Oct 20, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 20, 2023 | Oct 20, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2023 | Oct 24, 2023 | Administrative |
Electrical plan review Building Inspection · MECH-E | Oct 24, 2023 | Nov 3, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 20, 2023 | Nov 20, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 27, 2023 | Nov 27, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 29, 2023 | Nov 29, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 30, 2023 | Nov 30, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2023 | Dec 5, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 5, 2023 | Dec 6, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 7, 2023 | Dec 11, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 11, 2023 | Dec 12, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2023 | Dec 14, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $190,000
| Name | Role | License on permit |
|---|---|---|
| Pamela Robinson Smith Group | Architect | C25429 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026